Bug 132811 - don't make tasks for one resource concurrent
Summary: don't make tasks for one resource concurrent
Status: RESOLVED FIXED
Alias: None
Product: kplato
Classification: Unmaintained
Component: general (show other bugs)
Version: unspecified
Platform: Ubuntu Linux
: NOR wishlist
Target Milestone: ---
Assignee: Dag Andersen
URL:
Keywords:
Depends on:
Blocks:
 
Reported: 2006-08-22 16:14 UTC by Halla Rempt
Modified: 2007-02-09 09:15 UTC (History)
0 users

See Also:
Latest Commit:
Version Fixed In:
Sentry Crash Report:


Attachments

Note You need to log in before you can comment on or make changes to this bug.
Description Halla Rempt 2006-08-22 16:14:47 UTC
Version:           1.6 svn (using KDE KDE 3.5.4)
Installed from:    Ubuntu Packages

When I add a couple of tasks or subtasks to my project, tasks assigned to the same resource are placed in the same date-range. It would be nice to be able to limit the concurrency of a resource to one or more tasks per day (defaulting to one).
Comment 1 Dag Andersen 2007-02-09 09:15:00 UTC
*** Bug has been marked as fixed ***.