Bug 80112

Summary: More powerful Gantt diagrams in Korganizer
Product: [Applications] korganizer Reporter: Federico Zenith <zenith.federico>
Component: generalAssignee: Cornelius Schumacher <schumacher>
Status: RESOLVED DUPLICATE    
Severity: wishlist    
Priority: NOR    
Version First Reported In: 3.2.1   
Target Milestone: ---   
Platform: Compiled Sources   
OS: Linux   
Latest Commit: Version Fixed In:
Sentry Crash Report:

Description Federico Zenith 2004-04-22 11:09:59 UTC
Version:           3.2.1 (using KDE KDE 3.2.2)
Installed from:    Compiled From Sources
OS:          Linux

Hi,
I have been using Korganizer for quite a while and I really like the program. Among other things I translated the doucmentation to Italian.

I was wondering whether it could be possible to implement a more powerful gantt-diagram handling. Currently the %-approach in the To-Do list is fine for small projects, but I do miss a more detailed gantt, as the ones shown at this address:
http://www.ganttchart.com/Examples.html

The part I would find most useful is a superimposition of projects on a calendar, like in the first, basic example in the page above.

I think it could be implemented as an additional tab in the Edit To-Do window, with the %-bar in the project view working as a link to its status.

Cheers,
-Federico
Comment 1 Reinhold Kainhofer 2005-02-13 13:37:02 UTC

*** This bug has been marked as a duplicate of 72962 ***