| Summary: | Workflow Gantt chart starts at 2010 | ||
|---|---|---|---|
| Product: | [Applications] calligraplan | Reporter: | Daniil Vasin <danikvasin> |
| Component: | usability | Assignee: | Friedrich W. H. Kossebau <kossebau> |
| Status: | RESOLVED FIXED | ||
| Severity: | normal | CC: | dag.andersen |
| Priority: | NOR | ||
| Version First Reported In: | 2.9.7 | ||
| Target Milestone: | --- | ||
| Platform: | Kubuntu | ||
| OS: | Linux | ||
| Latest Commit: | Version Fixed/Implemented In: | 3.0.89 | |
| Sentry Crash Report: | |||
|
Description
Daniil Vasin
2016-03-16 21:44:49 UTC
Hmmm, possibly you opened the "Basic project" template? This is a small project created in 2010. Gantt chart only shows the range of the scheduled tasks so shows 2010. To change things you can edit the start/finish times in the Main Project dialog and reschedule. I can see how this is confusing, so need to think about it. Template system changed. Old templates not used anymore. |