Bug 356696

Summary: Not all tasks show up in Gantt chart
Product: [Applications] calligraplan Reporter: Felix Zesch <xelzifesch>
Component: generalAssignee: Friedrich W. H. Kossebau <kossebau>
Status: RESOLVED WORKSFORME    
Severity: grave CC: dag.andersen
Priority: NOR    
Version: 2.8.5   
Target Milestone: ---   
Platform: Other   
OS: Linux   
Latest Commit: Version Fixed In:
Attachments: calligraplan project file

Description Felix Zesch 2015-12-14 19:37:20 UTC
I have a project with several tasks. Only the first task is shown in the Gantt chart. The other tasks can only be seen in the WBS and all other views. So it seems as if "views" don't not work, only editing.

Reproducible: Always

Steps to Reproduce:
1. Open attached project
2. Click on task editor to view all tasks in the project
3. Click on Gantt chart to see that only one is shown.

Actual Results:  
Only one task is shown

Expected Results:  
All tasks which can be seen in the editor should be shown.

I use the German localization.
Comment 1 Felix Zesch 2015-12-14 19:38:54 UTC
Created attachment 96070 [details]
calligraplan project file
Comment 2 Dag Andersen 2016-08-26 09:14:42 UTC
Only scheduled tasks are shown in the gantt chart.
Unscheduled tasks don' have start/endtimes, but maybe add an option to show them anyway.
We'll see for 3.1
Comment 3 Dag Andersen 2016-09-01 09:04:19 UTC
Closer look: You have to also select the correct schedule to display.
You can select that at the bottom of the View Selector.