Summary: | Scheduler doesn't take actual finish times into account | ||
---|---|---|---|
Product: | [Applications] calligraplan | Reporter: | ishiki <genkaku> |
Component: | general | Assignee: | Dag Andersen <dag.andersen> |
Status: | RESOLVED NOT A BUG | ||
Severity: | normal | CC: | perso, renn0xtek9 |
Priority: | NOR | ||
Version: | 2.6.1 | ||
Target Milestone: | --- | ||
Platform: | Fedora RPMs | ||
OS: | Linux | ||
URL: | http://forum.kde.org/viewtopic.php?f=203&t=110291 | ||
Latest Commit: | Version Fixed In: | ||
Attachments: | Calligra plan file showing the bug |
Description
ishiki
2013-03-19 11:26:38 UTC
Created attachment 78199 [details]
Calligra plan file showing the bug
I confirm Task completion do not have any effect on actual planing in calligraplan :( You can add a sub-schedule to your schedule and reschedule the project. It will then take finished tasks and remaining effort into account when scheduling. *** Bug 320179 has been marked as a duplicate of this bug. *** |