Description Alvaro Soliverez 2013-07-27 20:53:12 UTC
When updating progress of a task, the Task Status view does not refresh accordingly.
If the task was already in the view (it shows tasks only within a timeframe or tasks in progress), it will not change groups if the task changes status.
If the task was not in the view, and for example, it is set to started, it will not show up in the view.

It the application is restarted, the tasks are shown correctly, so it's just an issue in the refresh of the view.