Version: 0.6.1 (using KDE 3.5.5 "release 45" , openSUSE 10.2) Compiler: Target: i586-suse-linux OS: Linux (i686) release 2.6.18.2-34-default 1) If resource calendar assigned with two time intervals: 9:00-13:00 14:00-18:00 Kplato displays resource allocation for first 4 hours only. Summary is also invalid. 2) If I have two tasks planned for the same day. Kplato doesn't warns about collision. So if I set interval as 9:00-17:00. I've got two tasks with 8 hours on the same day. It's impossible.
1) Fixed. The schedule (as shown in ganttchart) is correct but effort and cost calculations was incorrect. 2) This goes under the heading "Limited functionality" (still at 0.x revision). See Wish: 132811.
*** Bug has been marked as fixed ***.